What the mesh is, what it is becoming, and why. Implementation lives in the code repositories; the reasoning lives here. 00-GENESIS mission, engineering context, effect, and the rules that hold 01-RESEARCH investigations, before they harden into design 02-DESIGN the authoritative specification adr numbered decisions — what was chosen, and what was rejected DECISIONS.md the ledger: every decision, in the order it was taken Written for a reader who is not its author and has no access to the mesh it describes. Addresses use the documentation ranges of RFC 5737 and RFC 1918; nodes are named by role. Single initial commit by intent. The prior history came from a private repository and carried operational detail — a routable address identified as a VPN hub, real domain names, a hosting provider — which sanitising a tip commit would not have removed from the log.
This commit is contained in:
@@ -0,0 +1,150 @@
|
||||
# Work breakdown — the decomposition
|
||||
|
||||
How ADR 0001 gets built, in what order, and where a human must look.
|
||||
|
||||
Ordering is not preference. Each phase removes a constraint the next one needs gone.
|
||||
|
||||
---
|
||||
|
||||
## Rules of engagement
|
||||
|
||||
These exist so the work can run largely unattended without accumulating the kind of
|
||||
damage this refactor is meant to remove.
|
||||
|
||||
### Autonomous by default
|
||||
|
||||
An agent may, without asking:
|
||||
|
||||
- read anything, measure anything, query any database read-only
|
||||
- create branches, write code and tests, open pull requests
|
||||
- run the test suite and typechecks
|
||||
- write and update `hq/` documents
|
||||
|
||||
### Always stop and ask
|
||||
|
||||
- **destroying or overwriting data** — dropping a table, deleting a provision, rotating a
|
||||
live credential, removing a module from a node
|
||||
- **merging anything** — every merge is a human checkpoint, without exception
|
||||
- **a decision the ADRs do not already answer** — record the question in the relevant
|
||||
research effort rather than picking and moving on
|
||||
- **any change to `hq/00-GENESIS`** — it is stable by nature
|
||||
|
||||
### Definition of done for every task
|
||||
|
||||
1. tests written **and failing first**, then passing
|
||||
2. typecheck clean in every package the change touches
|
||||
3. the local mesh (Phase 0) comes up, and the behaviour is demonstrated in it
|
||||
4. `hq/` updated if the task changed or answered anything documented
|
||||
5. deployed, and **delivery verified on every node** — not "the pipeline was green"
|
||||
|
||||
### Non-negotiables carried from the current system
|
||||
|
||||
- **Never edit mesh-managed files on disk.** Use the owning tool.
|
||||
- **Never write to production databases directly.** Migrations for schema, application
|
||||
code for data.
|
||||
- **Every schema change ships twice** — consolidated schema *and* an incremental
|
||||
migration.
|
||||
- **Expand, then contract.** Add the new shape, migrate, verify, and only then remove the
|
||||
old one — never in a single step.
|
||||
- **A green pipeline proves transport, not effect.** Verify the effect.
|
||||
|
||||
---
|
||||
|
||||
## Phase 0 — A mesh that runs locally *(prerequisite)*
|
||||
|
||||
Nothing else starts until this exists. Every fault this refactor addresses was found in
|
||||
production because there was nowhere else to find it.
|
||||
|
||||
| # | task | done when |
|
||||
|---|---|---|
|
||||
| 0.1 | Container image for a node runtime | a node process starts in a container and registers |
|
||||
| 0.2 | Compose topology: broker, registry DB, object store, *n* nodes | `up` yields a mesh that elects a provider node and settles |
|
||||
| 0.3 | Seed a minimal mesh: nodes, one module, one provision | a module deploys end-to-end with no external service |
|
||||
| 0.4 | Run the pipeline inside it | a push-equivalent produces a cascade and a deployed artifact |
|
||||
| 0.5 | Fixtures for the failure modes already known | credential rotation reaching a running session; a provider deploy rotating a shared credential; a migration that ships nothing — each reproducible on demand |
|
||||
|
||||
**Checkpoint:** a human confirms the local mesh reproduces at least one bug from
|
||||
2026-08-22 before any decomposition begins.
|
||||
|
||||
---
|
||||
|
||||
## Phase 1 — Make the model expressible
|
||||
|
||||
The decomposition is impossible while a feature is a singleton per module.
|
||||
|
||||
| # | task | done when |
|
||||
|---|---|---|
|
||||
| 1.1 | ADR 0002 — named features, per-node opt-in | accepted |
|
||||
| 1.2 | Manifest: declared `features:` with type + directory | a module declares two of one kind and both build |
|
||||
| 1.3 | Selection: `always` / flavor-selected / `optional` | a node installs a subset; artifacts stay flavor-blind |
|
||||
| 1.4 | `requires:` moves onto the feature | a schema feature's database is not provisioned where the feature is not installed |
|
||||
| 1.5 | Assignment carries the opted-in feature set | opting a node in requires no rebuild |
|
||||
|
||||
**Checkpoint:** one existing module converted to declared features, deployed, verified —
|
||||
before any others follow.
|
||||
|
||||
---
|
||||
|
||||
## Phase 2 — Draw the boundary the domain already has
|
||||
|
||||
Cheapest first, and each one proves the extraction pattern before the expensive ones.
|
||||
|
||||
| # | task | extracted from | risk |
|
||||
|---|---|---|---|
|
||||
| 2.1 | `hal/knowledge` — one store, review workflow ported | hippocampus + noxflow `knowledge_*` | low — additive |
|
||||
| 2.2 | `hal/stream` — the record; notifications and messaging as views | axon, synapse, notifications, meetings, conversations | medium |
|
||||
| 2.3 | `hal/agents` — identity, licence, runs, memory, thoughts | noxflow agents, `hal/thoughts` | **high** — touches credentials |
|
||||
| 2.4 | `hal/work` — what remains of noxflow | noxflow tasks | medium |
|
||||
| 2.5 | `hal/ai` — provider integration, flavored | `hal/claude*` | medium |
|
||||
|
||||
Each extraction is expand-then-contract: new context alongside, dual-write, verify, cut
|
||||
over, remove. **Never a move commit.**
|
||||
|
||||
**Checkpoint:** after 2.1, a human confirms the extraction pattern before 2.2 begins.
|
||||
After 2.3, a human confirms credentials still reach every agent on every node.
|
||||
|
||||
---
|
||||
|
||||
## Phase 3 — Reclaim the kernel
|
||||
|
||||
Only possible once domains have modules to own their code.
|
||||
|
||||
| # | task | done when |
|
||||
|---|---|---|
|
||||
| 3.1 | Move work-domain code out of `hal/sdk` | `workflow-engine.ts`, `task-commands.ts` live in `hal/work` |
|
||||
| 3.2 | Move provider code out | `claude-credentials.ts` lives in `hal/ai` |
|
||||
| 3.3 | Move delivery code out | feature handlers, artifact manager, build executor live in `hal/delivery` |
|
||||
| 3.4 | Decide the residue | ADR: what `hal/sdk` keeps (open question 4) |
|
||||
|
||||
**Measure:** `hal/sdk` line count, tracked per task. Today: **34,636** across **155**
|
||||
files.
|
||||
|
||||
---
|
||||
|
||||
## Phase 4 — Separate what the mesh runs from the mesh
|
||||
|
||||
| # | task | done when |
|
||||
|---|---|---|
|
||||
| 4.1 | Decide the destination (open question 3) | ADR accepted |
|
||||
| 4.2 | Cross-repository dependency resolution proven | a catalogue module builds against a published `@hal/*` |
|
||||
| 4.3 | Move the 91 catalogue modules | this repository contains only mesh contexts |
|
||||
|
||||
**Checkpoint:** move one application first and run it for a week before the rest follow.
|
||||
|
||||
---
|
||||
|
||||
## Sequencing constraints
|
||||
|
||||
- **0 before everything.** Unverifiable refactors are how this list got long.
|
||||
- **1 before 2.** Extracting into contexts without per-node features recreates the module
|
||||
count inside the new names.
|
||||
- **2 before 3.** A domain can only own its shared code once the domain has a module.
|
||||
- **2.3 after 2.1 and 2.2.** Agents touch credentials; do it once the pattern is proven on
|
||||
cheaper contexts.
|
||||
- **4 last.** It is the only phase that is pure movement, so it is the only one safe to
|
||||
defer indefinitely.
|
||||
|
||||
## What "done" looks like
|
||||
|
||||
Eight contexts. `hal/sdk` holding only what is genuinely cross-cutting. A mesh that stands
|
||||
up on a laptop. A module count that grows only when the domain does.
|
||||