The correction the operator pushed: stop running a 20-minute lab against a mesh
mid-transformation, debugging paths the next phase deletes. The base-build hang
is almost certainly the SDK resolving from a git URL inside a docker build (issue
053), which Phase 2 removes — so debugging it on the current shape is debugging
deprecated code.
Phase 0 folds in: the installer's own regressions are fixed and committed;
whether it runs green is the final acceptance test, after the phases that change
its build path are in. Faults that can be reasoned out of the code path are, by
reading rather than running.
Claude-Session: https://claude.ai/code/session_01D6qtiYU3P9jk3pnAXyAFyx
Everything decided this cycle and not yet built. Phase 0 gets the installer
green, because nothing else is testable end to end without it. Phase 1 makes the
protocol one thing and fixes the Go/TS drift the installer's own provisioning
exercises. Phase 2 stands up the private package registry ADR 0014 assumes and
publishes the SDK into it. Phase 3 adopts the substrate so one postgres and one
lavinmq serve everything, which is the hardest and needs all three above.
Order is dependency, not preference. Each phase ends at a run rather than a
paragraph, because a phase that ends at a claim is how things went missing this
cycle without anything complaining.