Design 38's WP1-WP4b ran: the node's tool runtime is live on all four machines as the operator
account, tools are bundles given only their declared words, and a bundle has no bus credential.
So the wait on design 38 WP3 is over, the agent module calls nothing and the manager starts every
exchange (key, hand-over, waiting login, reconcile), and the manager's daemon now waits on WP4c's
record instead. Accounts are stated on all four, sudo -n works for each, the agent is installed on
all four; the plan's WP0 shrinks and WP2 gets a configuration-only live proof before any licence.
Designs 36 and 39 say what is built; this says in which order and what proves each step, in the
shape to-be 38 gave the operator's machine. Seven packages: the operator states the facts (accounts,
roles, licences); the console provides its endpoint; the licence manager and the agent module are
built and unit-tested in parallel; the manager goes live on the control node; the agent on one
workstation, with the switch and the predecessor's files removed as the proof of the whole; then the
rest of the nodes and the retirement of the two catalogue modules built on the old placement. The
live proofs wait for to-be 38's WP3, because both modules' tools run in the node's tool runtime
(ADR 0175) and a per-module tool container would rebuild what that record retires.