mesh/merge-gate pass: the change touches no module of the mesh's graph
mesh/repo-check pass: its merge-check.sh passed
mesh/delivery superseded: a newer head of the same pull request
ADR 0270 and 0271 accepted: their home in designs 47 and 45, and the glossary's final states
The operator accepted both on 2026-10-09. Design 47's state table gains covered and what ends a held
delivery by itself, and its group the wait for a composed check and the lift; design 45's signals table
gains S17 and its planned bus step says the wait is told at once. The glossary's delivery entry names its
six final states.
2026-10-09 09:24:30 +02:00
..

03-DESIGN

The authoritative specification. Implementation is built against what is written here.

Two layers

Folder What it is
00-as-is/ The mesh that exists today. Shipped behaviour, described as it is — including behaviour nobody would choose again.
01-to-be/ The mesh being built toward. Every statement traceable to a record in 02-DECISIONS/.

They are never mixed. A statement about the future does not belong in an as-is document, and an as-is document is never edited to describe an intention.

When a to-be design ships, it does not move. Its as-is counterpart is written or updated, the to-be document's status becomes implemented, and both stand — one describing what runs, the other recording what was intended. Deleting the intention loses the reasoning, which is the expensive half.

Frontmatter

Every design document (not the READMEs) carries:

---
layer: as-is | to-be
status: designed | in-progress | implemented | abandoned
code: []                 # owning code repo(s), from 00-META/repos.md
updated: YYYY-MM-DD      # date of the last status change, not of text edits
decisions: []            # 02-DECISIONS/ records this document rests on
---

For an as-is document, status: implemented is the normal state — it describes something that runs — and code: names where that implementation lives.

Status changes when implementation state changes, never because design text was edited. An implemented claim must be defensible from the owning repository's main branch, not from intent. If it cannot be checked, it is in-progress.

Cross-cutting views are generated from this frontmatter by the hq-status skill and never written to disk.

What belongs here

Functional analysis, architectural description, and specification — prose and diagrams only, no code. A manifest field may be named; a manifest may not be pasted. A document enters the to-be layer only after the decision behind it is recorded in 02-DECISIONS/ and the research that produced it is closed.

Subfolders are encouraged where a layer grows enough to need them.