jschoubben cb1954e7b5 Accept 0024, and rewrite the work breakdown around what is actually being done
**0024 accepted.** Model access was decided, built, and proven in the
lab, and two design documents rest on it; only the status had never
moved. The gate is green again.

**The work breakdown rewritten.** It planned a decomposition of the
existing system in place — extract contexts, declared features, shrink
the shared library. That is not the work. A replacement is being built
beside it, and only the old Phase 0 survived contact with reality, so
the one document meant to say what happens next was describing a system
being retired.

Now ordered by what "modules move across one at a time until the old
registry is off" actually requires:

- Phase 0 is marked done against the twenty-two lab assertions, **and
  carries its own limitation**: every module exercised was written to
  test the mechanism, so the vocabulary was shaped by its own fixtures.
- Phase 1 is the vocabulary gaps found by asking what real modules
  need — an object-store provision, a session as a licence consumer, a
  network shape with ordering, public certificate issuance.
- Phase 2 is one module, then a week of running it, because the point of
  going first is to find what Phase 1 missed.
- Phase 3 picks modules that each prove something the first did not; the
  mail system is last because it is the one that may send work back into
  the declaration language.
- Phase 4 is switching the registry off, named as a phase so it is not
  mistaken for the goal.

Keeps the rules of engagement unchanged — they were about how work is
done, not what it is — with one addition: stop and ask before anything
that touches a machine outside the lab.

Adds a section on keeping the list true, since the document it replaces
was wrong for weeks and nothing said so. A claim here is counted, not
reasoned, and a phase is done when the lab says so.
2026-08-31 17:25:27 +02:00

9.2 KiB

layer, status, code, updated, decisions
layer status code updated decisions
to-be designed
2026-08-31
02-DECISIONS/0001-mesh-brokers-nodes-host-agents-think.md
02-DECISIONS/0005-the-node-host.md
02-DECISIONS/0009-modules-and-the-graph.md
02-DECISIONS/0016-the-lab.md
02-DECISIONS/0028-the-substrate-supplies-the-control-plane-and-nothing-else.md

Work breakdown — replacing what provisions the mesh

Rewritten 2026-08-31. The previous version planned a decomposition of the existing system in place: extract contexts, convert modules to declared features, shrink its shared library. That is not what is being done — a replacement is being built beside it, and the old plan's Phase 0 was the only part that survived contact with it. So the document that was supposed to say what happens next had been describing work on a system being retired.

The goal, in one sentence

Modules move to the new mesh one at a time, until the old registry can be switched off.

Everything below is ordered by what that requires. Nothing here is a rewrite of the old system; its modules are the input.

Phase 0 — a mesh that runs — done

Not the code exists. Twenty-two assertions on real machines in the lab, each confirmed to fail when the behaviour is removed (ADR 0016, ADR 0017).

what is proven
a mesh comes into being a bare machine becomes one; others join with nothing but a token
credentials delivered to both ends with the mesh holding neither; rotated so the old one stops working
declarations survive reality a stopped machine is waited for; one that fell behind catches up unnamed; unassigning takes away exactly what it should; what the mesh says nothing about is left alone
failure is legible a machine that cannot do what it was told is named, with why
the mesh runs itself its own artifact store, and a builder that is a module the mesh assigns
names and reachability internal names, wildcards under a machine, containers reaching other machines, certificates the mesh issued, filtering that matches exactly what was declared
delivery a new commit reaches a machine already running the old one
model access answered by a record, with a key the mesh cannot read

What Phase 0 does not prove, and it is the important sentence in this document: every module exercised above was written to test the mechanism. No module from the existing system has ever run on this. The vocabulary was shaped by the things used to test it — the same fault as a fixture agreeing with the code it checks (04-ISSUES/005), at the scale of a design.

Phase 1 — the vocabulary a real module needs

Found by taking real modules and asking what they would require. Each is a gap in what can be expressed, not a defect in what is built.

# task done when
1.1 An object-store provision — a module can ask for a bucket (ADR 0028) a module requiring it is refused where nothing provides it, and given credentials where something does
1.2 A session as a consumer of a licence the two sessions on one machine hold different licences and each uses its own (14-model-access.md, ADR 0026)
1.3 A network shape, and ordering within a module a module of several containers reaches itself, and one that must start after another does
1.4 Public certificate issuance a name reachable from outside is served with a certificate from a public authority, obtained against a staging endpoint unless told otherwise (04-ISSUES/004)

1.1 blocks the first module; 1.3 and 1.4 block later ones and are listed now so they are not met as surprises. 1.3 is what a mail system needs and nothing else so far does.

Checkpoint: each is demonstrated in the lab before the module needing it is attempted.

Phase 2 — the first real module

# task done when
2.1 Port an object store module it runs on the new mesh, serves a bucket to another module, and its credential rotates
2.2 Run it beside the existing one both exist; nothing depends on the new one yet
2.3 Move one dependent onto it something real reads and writes through the new mesh's copy

Checkpoint, and it is a human one: it runs for a week before anything else moves. The point of going first is to find what Phase 1 missed, and a week is roughly how long that takes to show.

Phase 3 — the modules that prove the shape

Each exercises something the first one does not.

# task proves
3.1 An identity provider a module that is itself a provider — the provides/requires chain, with consumers requiring it
3.2 A forge a port claim against the machine's own daemon, and a module wanting both a database and an object store
3.3 A mail system several containers as one module, a private network between them, and names that are not one-per-node

3.3 is the hardest thing in this document and is deliberately last. If the declaration language turns out to be insufficient, it says so here.

Phase 4 — switch the old registry off

# task done when
4.1 Move the remainder nothing is assigned in the old system that is not assigned in the new one
4.2 Run in parallel, the old one authoritative for nothing a change to any module goes through the new mesh only
4.3 Switch it off it is stopped, and nothing notices

4.3 is a day's work and the phases above it are not. Naming it as a phase is what stops it being mistaken for the goal.

Sequencing

  • 1 before 2. Attempting a module without the vocabulary it needs produces a workaround, and a workaround in a manifest is a design decision taken by whoever was in a hurry.
  • 2 before 3, with the week. Moving three modules before running one is how three modules acquire the same defect.
  • 3.3 last. It is the only one that may send work back into the declaration language.
  • 4 cannot start early, and there is no partial credit. A registry still authoritative for one module is still running.

How this list is kept true

This section exists because the document it replaces was wrong for weeks and nothing said so.

A claim here is counted, not reasoned. The review of 2026-08-31 found a bundle described as carrying two images that carries three, a bootstrap described as needing six shapes that uses four, and ten documents calling themselves designed while naming lab-proven code. Each was produced by describing the system from its design instead of reading it.

A phase is done when the lab says so, and the lab keeps a receipt of when it last ran and against which commits. A phase marked done here whose assertions have not run is a claim about the past.

What is not proven gets said. Phase 0 is done and its limitation is written into it. A list that records only progress becomes a list nobody believes.

Rules of engagement

Unchanged from the previous version: they were about how work is done rather than what the work is.

Autonomous by default

Read anything, measure anything, query read-only. Create branches, write code and tests, run the suites, and write or update documents here.

Always stop and ask

  • destroying or overwriting data — dropping a table, deleting a provision, rotating a live credential, removing a module from a node
  • merging anything — every merge is a human checkpoint, without exception
  • anything touching a machine outside the lab, including a configuration change that restarts something people are using
  • a decision the records do not already answer — record the question rather than picking and moving on
  • any change to 00-META — it is stable by nature

Definition of done for every task

  1. tests written and failing first, then passing
  2. typecheck clean in every package the change touches
  3. the behaviour demonstrated in the lab, on real machines — not asserted
  4. documents here updated if the task changed or answered anything recorded
  5. delivered, and the effect verified — not that a pipeline was green

Non-negotiables

  • Never edit mesh-managed files on disk. Use the thing that owns the file.
  • Never write to a production database directly. Migrations for schema, application code for data.
  • Every schema change ships twice — consolidated schema and an incremental migration.
  • Expand, then contract. Add the new shape, migrate, verify, and only then remove the old one.
  • A green pipeline proves transport, not effect.

What "done" looks like

The old registry is off. Every module runs on the new mesh, declared rather than scripted. A machine that fails says what it could not do. And the number of modules grows when the work does, not when the platform needs somewhere to put something.