Date the SDK-before-users order of design 47's release 1-2 note by R4e
This commit is contained in:
@@ -737,7 +737,7 @@ release reports the controller's code lines against research 063's baseline (acc
|
||||
| R5 | The assigner writes what each node should run by its six rules, compared with what the controller sends, and the view shows every difference; the operator answers the asks that need no proof of who answered in the view (ADR 0437 §10) | 17 | mesh-delivery (assigner), mesh-controller (grants keys) | opened when it is prepared |
|
||||
| R6 | Each node applies from its wants, a new version reaches the module's canary first and the rest once it is healthy there, and the plans are deleted from the code | 18, 19 | the node-engine (`mesh-host`: the node agent), mesh-controller (plans deleted), mesh-delivery (the gate's delivery states go) | opened when it is prepared |
|
||||
|
||||
The issues are linked `depends-on` in this order; 976 depends on 975, and 979 also on 971. R3's prepare step on 2026-10-19 found ADR 0429 §20 contradicting itself and four release orders; ADR 0437 (accepted, the operator's Approve) cuts release 3 into R3a to R3d, each one release, and moves answering asks in the view to R5. R2c's prepare step on 2026-10-19 found one more order: the alive message is the only source of when the controller last heard a machine, which `nodes`, `node` and `status` read, so the controller takes that from presence (1183, R2c) and is delivered before the node-engine stops sending (1158, R2d); 1158 depends on 1183. In release 1-2, 1132 and 1136 depend on 1131, 1134 and 1135 on 1136, 1134 also on 1132 and 1128, and 1137 on 1134. Release 1-2 was confirmed as one milestone; its prepare step on 2026-10-18 found the release orders hidden in it, and the operator chose at 18:52 to cut it by them, so it is the milestones R1a to R2d above, each one release (the operator, 2026-10-19: a milestone is one release): an SDK change still ships before its users until release 4 (ADR 0429 §10); a new key on the wire goes only to a node that says it reads it; a new repository's first module registers at its merge's Approve (ADR 0432, issue 1146); the bus gives the watchman connect events only through a system account (ADR 0431); and release 2's other gaps are settled by ADR 0433 and ADR 0434. A node that is down has no effect on a delivery and plays what it missed when it returns (ADR 0435, the operator, 2026-10-18; issues 1160, 1161). Milestone 3's first live group (milestone 4's, on 2026-10-17) held one Approve but merged in two passes and went out in two delivery plans: a member's tests read the other member's repository, so the first merge made the second's verdict out of date, and a closed group never asked its composed verdict again (issues 1049, 1082). The operator put a fix of milestone 3 after milestone 4 and before milestone 5 on 2026-10-18; acceptance test 1 is proved again by it. The operator put milestone 5b after milestone 5 and before milestone 6 on 2026-10-18, as an issue rather than a research effort; where the planning goes is settled by a decision record before it is built (issue 1117), and milestone 6's build changes are read against it. Milestone 2b was
|
||||
The issues are linked `depends-on` in this order; 976 depends on 975, and 979 also on 971. R3's prepare step on 2026-10-19 found ADR 0429 §20 contradicting itself and four release orders; ADR 0437 (accepted, the operator's Approve) cuts release 3 into R3a to R3d, each one release, and moves answering asks in the view to R5. R2c's prepare step on 2026-10-19 found one more order: the alive message is the only source of when the controller last heard a machine, which `nodes`, `node` and `status` read, so the controller takes that from presence (1183, R2c) and is delivered before the node-engine stops sending (1158, R2d); 1158 depends on 1183. In release 1-2, 1132 and 1136 depend on 1131, 1134 and 1135 on 1136, 1134 also on 1132 and 1128, and 1137 on 1134. Release 1-2 was confirmed as one milestone; its prepare step on 2026-10-18 found the release orders hidden in it, and the operator chose at 18:52 to cut it by them, so it is the milestones R1a to R2d above, each one release (the operator, 2026-10-19: a milestone is one release): an SDK change still ships before its users until R4e (ADR 0429 §10, ADR 0453 clause 2); a new key on the wire goes only to a node that says it reads it; a new repository's first module registers at its merge's Approve (ADR 0432, issue 1146); the bus gives the watchman connect events only through a system account (ADR 0431); and release 2's other gaps are settled by ADR 0433 and ADR 0434. A node that is down has no effect on a delivery and plays what it missed when it returns (ADR 0435, the operator, 2026-10-18; issues 1160, 1161). Milestone 3's first live group (milestone 4's, on 2026-10-17) held one Approve but merged in two passes and went out in two delivery plans: a member's tests read the other member's repository, so the first merge made the second's verdict out of date, and a closed group never asked its composed verdict again (issues 1049, 1082). The operator put a fix of milestone 3 after milestone 4 and before milestone 5 on 2026-10-18; acceptance test 1 is proved again by it. The operator put milestone 5b after milestone 5 and before milestone 6 on 2026-10-18, as an issue rather than a research effort; where the planning goes is settled by a decision record before it is built (issue 1117), and milestone 6's build changes are read against it. Milestone 2b was
|
||||
put before milestone 3 by the operator on 2026-10-17. Milestone 3 builds ADR 0418, ADR 0419 and ADR 0421
|
||||
(issues 977, 978 and 1022), and splits mesh-controller's unit tests from its integration tests (issue 895, the
|
||||
operator on 2026-10-17), so the unit level holds its bound of ADR 0391; the integration level's sixty seconds
|
||||
|
||||