@@ -418,7 +418,7 @@ planner, the rollout). **Downstream of** Module, Core, Health and repair and Dat
|
||||
(ADR 0237).
|
||||
*Not:* ~~build machine~~
|
||||
- **build queue** — the builds waiting to run, kept by the bus as three work queues a builder takes in order:
|
||||
delivery builds, then checks of pull requests marked ready, then every other check; each check queue keeps one
|
||||
delivery builds, then checks of pull requests whose Approve is asked or given (ADR 0421 §10), then every other check; each check queue keeps one
|
||||
request per pull request, the newest (ADR 0406); one entry in it is a
|
||||
**build request**.
|
||||
The queue's verbs still say *ask* for an entry; the conversation's ask is another thing
|
||||
|
||||
@@ -58,7 +58,7 @@ A design becomes **milestones**, and each milestone becomes **issues**:
|
||||
owns what is not. The knowledge base's rule `deferral` checks the decision record when it is proposed
|
||||
([issue 354](../../04-ISSUES/354-a-decided-rename-was-never-scheduled-and-the-operator-believed-it-live/00-report.md)).
|
||||
- HQ is not a code repository and never carries implementation.
|
||||
- How the building is done — worktrees, agents, review, checks, the ready mark and the delivery — is playbook
|
||||
- How the building is done — worktrees, agents, review, checks, the Approve and the delivery — is playbook
|
||||
07's, not this one's.
|
||||
|
||||
## How it is checked
|
||||
|
||||
@@ -28,7 +28,8 @@ A small fix (one repository, one issue, about an hour of work) follows
|
||||
hours of local work, met its first check on 2026-10-16 and failed on 29 problems, TypeScript errors among
|
||||
them, that a unit suite run continuously while working finds at once.
|
||||
- **A green pull request nobody marks.** An approved, green pull request that was not marked ready waited
|
||||
12 h 17 min for someone to merge it (mesh-catalog #300, 2026-10-14).
|
||||
12 h 17 min for someone to merge it (mesh-catalog #300, 2026-10-14). There is no ready mark since ADR 0421:
|
||||
the operator's Approve is asked as soon as the checks pass.
|
||||
- **A module proven only after it reached the machines.** The mail modules were delivered with unit tests
|
||||
only, then failed live three times (issues 859, 865, 868) and took five more hours of fixes.
|
||||
|
||||
@@ -95,6 +96,10 @@ never into the running one, unless it blocks the running one.
|
||||
modules its delivery plan moves, to which machines); and for a group, its merge order. The context file
|
||||
points to these notes; an issue reread by another session or a later agent then holds what was found.
|
||||
When the reading is large, it starts with a read-only survey agent on the smaller model.
|
||||
**The survey sizes each issue, and an issue sized over an hour is split before any agent starts** (the operator,
|
||||
2026-10-17), into issues of about 30 minutes each, one change each, in the order they land: the bound of a
|
||||
fixing agent's issue is then a real bound. On 2026-10-17 one issue held four changes sized at four to six
|
||||
hours; it ran past its 30-minute bound for over an hour, and the reports could only say "still on part D".
|
||||
6. **Move the issues to `fixing`**, `by` naming the feature's agent for that repository.
|
||||
|
||||
## Step 1 — Develop (one fixing agent per repository, smaller model)
|
||||
@@ -114,7 +119,10 @@ never into the running one, unless it blocks the running one.
|
||||
message ("issue 805: landing in mesh-catalog"); reach the mesh only through the mesh MCP server, never ssh;
|
||||
never push, open, merge or close a pull request; never write to a store's database by hand, a schema change
|
||||
is a numbered migration and the consolidated schema; Go only unless the context file says otherwise; never
|
||||
move another issue. Report back in under 150 words: commits, tests added and that they failed first, the
|
||||
move another issue; **never run an integration test locally** (no `go test -tags integration`, no `merge-check.sh`,
|
||||
no bus or store test run): compile them with `go vet -tags integration ./...` and leave the running to the
|
||||
forge's merge check. On 2026-10-17 three fixing agents ran them anyway, one for minutes on end, because the
|
||||
brief only said they wait for the check (the operator). Report back in under 150 words: commits, tests added and that they failed first, the
|
||||
check results, anything you stopped on.
|
||||
- **An agent that finds the code differs from its context file stops and reports** (file:line); the lead
|
||||
settles it, updates the context file, and continues the agent.
|
||||
@@ -132,7 +140,7 @@ never into the running one, unless it blocks the running one.
|
||||
the tree that is pushed.
|
||||
2. **One reviewer reads every repository's local commits** together, against the context files and the
|
||||
decisions. **It is one agent, kept for the whole release** like the fixing agents: the lead continues it by
|
||||
its id for every later round, for the extra cycle after a failed check (step 3) and for the ready mark, so it
|
||||
its id for every later round, for the extra cycle after a failed check (step 3) and for its review record, so it
|
||||
reads the decisions, the issues, the context files and the commits once (issue 1042). A fresh reviewer per
|
||||
round or per mark pays for all of that again. Its report is per repository: each finding as file:line, the failure it causes, and the fix.
|
||||
It says which round it is in ("round 1 of at most 3").
|
||||
@@ -152,7 +160,11 @@ never into the running one, unless it blocks the running one.
|
||||
run only in the merge check (the operator, 2026-10-16), never before. Pull requests in two or
|
||||
more repositories that share the branch name are one delivery group (ADR 0239 §2).
|
||||
Where a session pushes through the forge tool `gitea_commit` (one commit on the forge's current base), the
|
||||
reviewer first confirms that commit's tree equals the reviewed one.
|
||||
reviewer first confirms that commit's tree equals the reviewed one. **Each pull request's description carries
|
||||
the review record** (ADR 0421 §5), one line the lead writes from the reviewer's approval:
|
||||
`Reviewed-by: <who@node> at <full sha>` (the issue 1022 note gives its form). mesh-delivery reads it at every new
|
||||
head and puts it in the Approve's ask; a missing line, or one naming another commit, is said first in the ask.
|
||||
It is never a gate.
|
||||
2. **The forge's merge checks run the integration tests once** (`mesh/merge-gate`, `mesh/repo-check`). No
|
||||
second review: step 2 reviewed this tree.
|
||||
3. **A check that fails** goes back to the same reviewer, continued by its id, with the failure, for **one more cycle** of step 2 with
|
||||
@@ -162,17 +174,21 @@ never into the running one, unless it blocks the running one.
|
||||
on 2026-10-17 it showed a store test's `FAIL` without its cause, and a fix was first guessed from the code.
|
||||
**A change to `merge-check.sh` is judged by main's version of it**, so a test the change adds must pass under
|
||||
either version: one that runs the new script's behaviour runs a file of its own, never `merge-check.sh` itself.
|
||||
4. **The milestone's acceptance is proven before it is marked ready.** A milestone that adds or changes a module
|
||||
**So a change that needs the new script to judge it ships the script first, as a small fix of its own**, and the
|
||||
rest waits for its delivery: on 2026-10-17 milestone 3 of design 47 moved its integration tests behind a build
|
||||
tag in the same pull request as the script that runs that tag, and main's script would have skipped every
|
||||
tagged test, its acceptance tests among them. The prepare step looks for this: a change to `merge-check.sh` or to
|
||||
what it selects (build tags, the store-tests list) is cut ahead of the milestone.
|
||||
4. **The milestone's acceptance is proven by its check.** A milestone that adds or changes a module
|
||||
carries an integration test that starts the module whole, its process against the real bus and store, and
|
||||
shows the milestone's acceptance sentence; the forge's checks run it (ADR 0391 §1, §6). Unit tests alone are not
|
||||
that proof; the mesh has no end-to-end tests yet, and the lab is not used (the operator, 2026-10-16).
|
||||
5. **The reviewer marks each pull request ready as soon as the acceptance is shown.** It does not wait for the
|
||||
checks itself: a watcher waits for them and wakes the lead, who continues the reviewer by its id to mark
|
||||
(issue 1042). It marks with
|
||||
`mesh-delivery.mark-ready` (the delivery of the head it approved, who reviewed it and why), which writes the
|
||||
label `mesh/ready` and then `ready at <full sha>`, the order the forge counts (issue 913); mesh-delivery merges it when its checks pass
|
||||
and the operator approved the merge into main on Telegram, the channel that proves who answered today (ADR 0364,
|
||||
ADR 0398 §3; an Approve at the terminal is issue 953). Beyond that
|
||||
5. **The operator's Approve is asked as soon as the checks pass** (ADR 0421). Nobody marks, labels, comments or
|
||||
rechecks: mesh-delivery asks the Approve on Telegram, the channel that proves who answered today (ADR 0398 §3;
|
||||
an Approve at the terminal is issue 953), once both checks passed, for a delivery group once for all its
|
||||
members, naming the review record. On the Approve it merges the approved heads, a group's in one pass
|
||||
(ADR 0418). A new head ends the Approve and is asked again once its checks pass. A watcher follows the checks,
|
||||
the Approve and the merge, and wakes the lead. Beyond that
|
||||
Approve, the operator's word is waited for only when the milestone changes what the operator sees, removes
|
||||
data, or needs a step only the operator's terminal can take; the lead says which before the milestone starts.
|
||||
|
||||
@@ -203,7 +219,7 @@ survive.
|
||||
| The lead (step 0 decisions, the context files, following and reporting) | larger | judgement |
|
||||
| Read-only questions about the code for the context files | smaller | reading, answered with file:line |
|
||||
| Fixing agents (step 1, and the fixing in steps 2 and 3) | smaller | building to a written context |
|
||||
| The reviewer (step 2, the extra cycle in step 3 and the ready mark; one agent, continued by its id) | larger | judgement, once per round |
|
||||
| The reviewer (step 2, the extra cycle in step 3 and the review record; one agent, continued by its id) | larger | judgement, once per round |
|
||||
| Decision records | larger | judgement |
|
||||
|
||||
Every agent the mesh runs draws on one weekly allowance shared by every session, and the larger model
|
||||
@@ -220,8 +236,8 @@ on, with when it started and its bound.
|
||||
| a fixing agent's issue | 30 minutes | ask it where it stands; split or take over |
|
||||
| the review | 15 minutes a round | ask the reviewer; stop at round 3 |
|
||||
| a merge check | 15 minutes | read the build queue (`mesh-controller.queue`) and the check's log |
|
||||
| the ready mark | 15 minutes after the acceptance is shown | the reviewer marks it, or the lead does |
|
||||
| a merge after ready | 5 minutes after the checks pass | read `mesh-delivery.show` for the delivery |
|
||||
| the Approve's ask | 5 minutes after both checks pass | read `mesh-delivery.show`: an ask not raised is a fault, said to the operator |
|
||||
| a merge after the Approve | 5 minutes | read `mesh-delivery.show` for the delivery |
|
||||
| a delivery plan | its class's budget (`mesh-delivery.times`), at most 30 minutes | read `mesh-controller.plans`, then `mesh-delivery.stalled` |
|
||||
|
||||
**Every wait on the list has a watcher** (the operator, 2026-10-17). A session runs only when a message reaches
|
||||
@@ -235,7 +251,7 @@ a minute. After every answer or timeout it reads the state from the verb that ow
|
||||
`mesh-controller.plans`, `knowledge-base.get`), because an event only wakes it (ADR 0367). It finishes, and so wakes
|
||||
the lead, when the state changes or the wait passes its bound. The lead never sleeps or polls by hand to wait.
|
||||
|
||||
**Every five minutes, every two minutes while a delivery plan runs, and at once when something lands, stops or
|
||||
**Every ten minutes (the operator, 2026-10-17), every two minutes while a delivery plan runs, and at once when something lands, stops or
|
||||
needs the operator,** the lead reports, in one of the two layouts below (the operator, 2026-10-16: an overview
|
||||
of the issues, often). Times are local and absolute, from the clock (`date`), never guessed; every number has its
|
||||
unit and its bound or baseline; an issue is named by its number and a few words, never by its number alone.
|
||||
@@ -318,6 +334,8 @@ issues in `fixing` that nobody works on reads to the operator as stuck work.
|
||||
request into a feature branch exists. A pull request per issue, or an agent waiting on a merge check in
|
||||
step 1, is the failure this playbook prevents.
|
||||
- A context file exists per touched repository under `.work/<slug>/` while the feature runs.
|
||||
- No issue of a running milestone is sized over an hour in its prepare note; an issue whose fixing agent passes
|
||||
twice its bound was not split.
|
||||
- Every issue of a running milestone has a note from the prepare step naming its files and tests (file:line), how
|
||||
it is checked and delivered, and for a group its merge order (`issue-tracker.get`); an issue moved to `fixing`
|
||||
without one is a prepare step skipped.
|
||||
@@ -343,12 +361,13 @@ issues in `fixing` that nobody works on reads to the operator as stuck work.
|
||||
stay in `fixing` for more than a working day, is the smell: stop and bring it to the operator.
|
||||
- A review report that asks a change outside the issues' done-when, or a fourth round, is the failure of the
|
||||
review rules; `issue-tracker.list` with `flag: abandoned` lists issues left in `fixing` with nobody on them.
|
||||
- A pull request reviewed and green but not marked ready for more than 15 minutes is a lead that did not
|
||||
mark it.
|
||||
- Every ready mark of a release names one reviewer (`mesh-delivery.show`, `ready.by`), and the lead's save point
|
||||
names one reviewer id per release; a second reviewer within one release is a reviewer not kept (issue 1042).
|
||||
- A milestone that adds or changes a module marked ready with no integration test that starts the module whole is
|
||||
the failure of the check step's fourth item.
|
||||
- A pull request green for more than 5 minutes with no Approve asked is a fault of mesh-delivery
|
||||
(`mesh-delivery.show`), said to the operator.
|
||||
- Every review record of a release names one reviewer (`mesh-delivery.show`, the review record), and the lead's
|
||||
save point names one reviewer id per release; a second reviewer within one release is a reviewer not kept
|
||||
(issue 1042). A pull request whose ask says it has no review record at its head is a record not written.
|
||||
- A milestone that adds or changes a module whose pull request has no integration test that starts the module
|
||||
whole is the failure of the check step's fourth item.
|
||||
- A bed run from `.work/<slug>/mesh-lab` that fails naming a `.work/<slug>/<repo>/…` path it cannot find is a
|
||||
missing sibling worktree, not a mesh fault.
|
||||
|
||||
|
||||
@@ -39,16 +39,15 @@ one delivery**. Everything before the push is local and fast.
|
||||
model; at most 3 rounds, as playbook 07; from round 2 only what is wrong; a finding outside the issue's
|
||||
done-when is opened as an issue of its own, never asked as a change). The reviewer's findings go back to the same agent that wrote the fix, continued by
|
||||
its id, so the fix keeps its context. A playbook or design edit of a few lines may skip the reviewer: the
|
||||
operator's word on the pull request is its review, and the lead marks it ready on that word.
|
||||
operator's Approve of its merge is its review, and the review record says so.
|
||||
5. **Push once and open the pull request.** The trunk is what runs and nothing holds merged work back
|
||||
(ADR 0401), so a fix waits for no other change's delivery. The forge's merge
|
||||
check runs the integration tests, the only
|
||||
place they run (the operator, 2026-10-16). A failed check
|
||||
goes back to the same agent with the failure, and the reviewer reads only the change it makes.
|
||||
6. **The reviewer marks it ready at once** (for an edit that skipped the reviewer, the lead, on the
|
||||
operator's word) with `mesh-delivery.mark-ready` (the delivery of the head it approved, who reviewed it and
|
||||
why), which writes the label `mesh/ready` and then `ready at <full sha>`, the order the forge counts (issue 913);
|
||||
mesh-delivery merges it when its checks pass. A fix to a module that changes how it runs carries an
|
||||
6. **The pull request's description carries the review record** (`Reviewed-by: <who@node> at <full sha>`,
|
||||
playbook [07](07-feature-branches.md) step 3), and mesh-delivery asks the operator's Approve as soon as its
|
||||
checks pass and merges the approved head (ADR 0421); nobody marks, labels, comments or rechecks. A fix to a module that changes how it runs carries an
|
||||
integration test starting the module whole against the real bus and store, run by the forge's checks
|
||||
(ADR 0391 §1, §6); unit tests alone are not that proof, and the lab is not used. The operator's word is waited for only when the fix changes what the operator sees, removes data,
|
||||
or needs the operator's terminal.
|
||||
@@ -78,9 +77,9 @@ code.
|
||||
|---|---|---|
|
||||
| building the fix | 1 hour | it is a feature: stop and plan it under playbook 07 |
|
||||
| the review | 15 minutes | ask the reviewer where it stands |
|
||||
| the ready mark | 15 minutes after the review approved | the reviewer marks it, or the lead does |
|
||||
| the merge check | 15 minutes | read `mesh-controller.queue` and the check's log |
|
||||
| the merge after ready | 5 minutes after the checks pass | read `mesh-delivery.show` for the delivery |
|
||||
| the Approve's ask | 5 minutes after both checks pass | read `mesh-delivery.show`: an ask not raised is a fault, said to the operator |
|
||||
| the merge after the Approve | 5 minutes | read `mesh-delivery.show` for the delivery |
|
||||
| the delivery plan | its class's budget (`mesh-delivery.times`), at most 30 minutes | read `mesh-controller.plans`, then `mesh-delivery.stalled` |
|
||||
|
||||
A wait past its bound is said to the operator at once, with what is being done about it.
|
||||
@@ -95,8 +94,8 @@ reading itself and uses one subagent only for the review.
|
||||
- A small fix has one pull request with one or few commits naming its issue, opened after its review: a pull
|
||||
request with many heads is a fix reviewed after its push.
|
||||
- Its issue moves to `resolved` within the hour its delivery plan ends.
|
||||
- A pull request reviewed and green but unmarked
|
||||
for more than 15 minutes, a fix to a module's running marked ready with no integration test of the module whole, or a review report
|
||||
- A pull request with no review record at its head (the Approve's ask says so first), a fix to a module's
|
||||
running pushed with no integration test of the module whole, or a review report
|
||||
asking a change outside the issue's done-when, is the failure of steps 4 to 6.
|
||||
- An issue in `fixing` with nobody on it shows in `issue-tracker.list` with `flag: abandoned`; a stopped fix
|
||||
moves it back to `open` with its note.
|
||||
|
||||
@@ -558,7 +558,8 @@ when the previous one's delivery is done.
|
||||
The issues are linked `depends-on` in this order; 976 depends on 975, and 979 also on 971. Milestone 2b was
|
||||
put before milestone 3 by the operator on 2026-10-17. Milestone 3 builds ADR 0418, ADR 0419 and ADR 0421
|
||||
(issues 977, 978 and 1022), and splits mesh-controller's unit tests from its integration tests (issue 895, the
|
||||
operator on 2026-10-17), so its checks hold the bounds of ADR 0391. Acceptance test 6 spoke of a ready mark when milestone 2 was delivered; restated for
|
||||
operator on 2026-10-17), so the unit level holds its bound of ADR 0391; the integration level's sixty seconds
|
||||
is issue 1055. Acceptance test 6 spoke of a ready mark when milestone 2 was delivered; restated for
|
||||
the Approve, it is proved again by milestone 3.
|
||||
|
||||
## What is not decided here
|
||||
|
||||
Reference in New Issue