@@ -12,8 +12,12 @@ A design becomes **milestones**, and each milestone becomes **issues**:
- **A milestone is usable on its own.** Once its delivery plan is done, the operator or the mesh can do
something new, said in one sentence ("a Claude Code session is mirrored into a thread on the bus").
A milestone that changes nothing anyone can use is not a milestone; fold it into the next.
- **A milestone is one feature step** of playbook [07](07-feature-branches.md): prepared, developed in one to
two hours, reviewed, checked and delivered as one. A milestone larger than that is split.
- **A milestone is one release** of playbook [07](07-feature-branches.md): prepared, developed whole, reviewed,
checked and delivered as one, never cut for its size or for time (the operator, 2026-10-17).
- **Milestones are cut by release order.** A milestone ends where one repository's change must be released before
another can use it (a new manifest word before the catalogue reads it, an SDK change before its users, until
design 47's milestones 3 and 6 lift those orders); the lead checks this when cutting, so no milestone needs a
second release.
- **An issue is one repository's part of a milestone,** sized so a fixing agent finishes it inside the
milestone's development time. Issues that must land in order are linked `depends-on`.
@@ -40,9 +44,9 @@ A design becomes **milestones**, and each milestone becomes **issues**:
entry in the design.
7. **Flip the status.** `status: in-progress`, `updated:` today; the design change goes through playbook
[08](08-small-fixes.md) (one hq pull request).
8. **Hand each milestone to playbook 07, one at a time.** The milestone is the feature step; its issues are the
step's issues; the next milestone starts when the previous one's delivery plan is done. A design waits while
another design's milestones are being built: one design is built at a time (playbook
8. **Hand each milestone to playbook 07, one at a time.** The milestone is one release of playbook 07; its issues
are the release's issues; the next milestone starts when the previous one's delivery plan is done. A design waits
while another design's milestones are being built: one design is built at a time (playbook
[07](07-feature-branches.md)), so this step starts only when the design before it is delivered.
9. **On completion of the last milestone**, run the "when something ships" section of playbook
[02](02-graduation.md).
+22 -22
View File
@@ -40,14 +40,16 @@ opened **once**, after the review. It runs in five phases, and its time is bound
| Phase | What happens | Bound |
|---|---|---|
| 0. Prepare | the lead settles the open questions and writes one context file per repository | 15 minutes |
| 1. Develop | one fixing agent per repository builds every issue locally, unit tests only | 1 to 2 hours |
| 1. Develop | one fixing agent per repository builds every issue locally, unit tests only | the milestone's issues, 30 minutes each |
| 2. Review | one reviewer reads all of it; reports go both ways; at most 3 rounds | 15 minutes |
| 3. Check | push; the forge's merge checks run the integration tests; no further review | one check run |
| 4. Deliver | merge; the delivery plan builds, publishes and sends the whole feature | its delivery plan |
A feature that cannot be developed in about two hours is split into **steps**. Each step runs all five
phases on its own; the next step starts only when the previous step's delivery plan is done. A step is the
unit that ships, so nothing finished waits for work that is not.
**One milestone is one release** (the operator, 2026-10-17). A milestone is developed whole, reviewed once,
pushed once and delivered once. It is never cut into steps for its size or for time: every cut adds a review, a
merge check, an Approve and a delivery plan of waiting, so the fewest cuts is the fastest. Milestones are cut by
release order when the design is broken up (playbook [04](04-build-handoff.md)); a release-order dependency found
inside a milestone is a fault of that cut, said to the operator, never a silent extra step.
**One design is built at a time** (the operator, 2026-10-17). While the milestones of one design are being
built, no milestone of another design starts: its issues stay `open`, and nobody moves them to `diagnosing` or
@@ -55,16 +57,14 @@ built, no milestone of another design starts: its issues stay `open`, and nobody
lead who finds another design's milestone already in `fixing` asks its owner before starting its own. A small
fix ([playbook 08](08-small-fixes.md)) and an issue that is in no design's milestones are not held by this rule.
**Scope is fixed at phase 0.** An issue found during a feature goes to the next step or the next feature,
**Scope is fixed at phase 0.** An issue found during a feature goes to the next milestone or the next feature,
never into the running one, unless it blocks the running one.
## Phase 0 — Prepare (the lead, larger model)
1. **Name the feature once:** `feat/<slug>`, the same branch name in every repository it touches. The
branch is never protected. **One milestone is one branch per repository** (the operator, 2026-10-17): every
step of a milestone uses the milestone's one name and its one folder `.work/<slug>/`; after a step's merge,
which removes the branch on the forge, the next step makes it again from the new `main` under the same name.
Never a second name for a step (`-2`, `-step2`).
branch is never protected. **One milestone is one branch per repository** (the operator, 2026-10-17), with one
folder `.work/<slug>/`; never a second name for part of it (`-2`, `-step2`).
2. **Make the worktrees:** one per touched repository under `.work/<slug>/<repo>`, branched off `main`
(`git worktree add .work/<slug>/<repo> -b feat/<slug> origin/main`). The lab beds find the other
repositories by sibling path, so add the untouched siblings the lab reads as detached worktrees on
@@ -144,21 +144,21 @@ never into the running one, unless it blocks the running one.
second review: phase 2 reviewed this tree.
3. **A check that fails** goes back to the reviewer with the failure, for **one more cycle** of phase 2 with
the same fixing agents; then push once again.
4. **The step's acceptance is proven before it is marked ready.** A step that adds or changes a module
4. **The milestone's acceptance is proven before it is marked ready.** A milestone that adds or changes a module
carries an integration test that starts the module whole, its process against the real bus and store, and
shows the step's acceptance sentence; the forge's checks run it (ADR 0391 §1, §6). Unit tests alone are not
shows the milestone's acceptance sentence; the forge's checks run it (ADR 0391 §1, §6). Unit tests alone are not
that proof; the mesh has no end-to-end tests yet, and the lab is not used (the operator, 2026-10-16).
5. **The reviewer marks each pull request ready as soon as the acceptance is shown** with
`mesh-delivery.mark-ready` (the delivery of the head it approved, who reviewed it and why), which writes the
label `mesh/ready` and then `ready at <full sha>`, the order the forge counts (issue 913); mesh-delivery merges it when its checks pass
and the operator approved the merge into main on Telegram, the channel that proves who answered today (ADR 0364,
ADR 0398 §3; an Approve at the terminal is issue 953). Beyond that
Approve, the operator's word is waited for only when the step changes what the operator sees, removes
data, or needs a step only the operator's terminal can take; the lead says which before the step starts.
Approve, the operator's word is waited for only when the milestone changes what the operator sees, removes
data, or needs a step only the operator's terminal can take; the lead says which before the milestone starts.
**One exception: a catalogue change that uses a new manifest word.** The catalogue's merge check reads
manifests with the controller the mesh runs, so the controller's pull request is merged and delivered first;
then `mesh-delivery.recheck` the catalogue's and merge it on the new verdict. Plan such a feature as two steps.
then `mesh-delivery.recheck` the catalogue's and merge it on the new verdict. Such work is two releases, the controller's first, and playbook 04 cuts its milestones that way.
The exception ends when milestone 3 of design 47 is delivered (issue 977, ADR 0402, ADR 0403): the group's composed
check, judged by the group's controller, is then each member's gate, and the feature is one group.
@@ -207,7 +207,7 @@ unit and its bound or baseline; an issue is named by its number and a few words,
waits for, marked ✓ landed, ▶ fixing, ⏸ waiting, ✗ stopped:
```
Feature <slug> · step <n> of <m> · phase <name>, <minutes used> of <bound> min
Feature <slug> · milestone <n> of <m> · phase <name>, <minutes used> of <bound> min
Issues: <landed> of <total> landed · <fixing> fixing · <waiting> waiting
mesh-controller (agent: fixing, 2 of 3 landed)
@@ -228,11 +228,11 @@ Next: <the next action, one line>
**The short layout** (on a channel such as Telegram, or when nothing changed but time):
```
<slug> step <n>/<m> · <phase> <used>/<bound> min · <landed>/<total> landed · past bound: <none | what> · needs you: <nothing | what> · week <n> %
<slug> milestone <n>/<m> · <phase> <used>/<bound> min · <landed>/<total> landed · past bound: <none | what> · needs you: <nothing | what> · week <n> %
```
A report says what changed since the last one first. In the session every report is the full layout, the whole
tree of the step's issues included, also when only time passed: the operator reads the state from it without
tree of the milestone's issues included, also when only time passed: the operator reads the state from it without
asking. The short layout is for a channel.
## The context of the lead's own session
@@ -250,9 +250,9 @@ left, its frontmatter still saying `designed`, read to another session as not bu
was started beside it (issue 1009, 2026-10-17). So the lead writes the design's state back at each of these
moments, the same hour, an hq change going through [playbook 08](08-small-fixes.md):
- **The first step starts:** the design's `status: in-progress` ([playbook 04](04-build-handoff.md) step 7),
- **The first milestone starts:** the design's `status: in-progress` ([playbook 04](04-build-handoff.md) step 7),
if it is not already.
- **A step's delivery plan is done:** its issues are resolved (phase 4), and the design's milestone entry says
- **A milestone's delivery plan is done:** its issues are resolved (phase 4), and the design's milestone entry says
it is delivered, with the date.
- **The building pauses with work left** (another design takes its turn, a hand-over, the session's end): the
design stays `in-progress`, and each issue left gets a note with `issue-tracker.note` saying what it waits
@@ -263,7 +263,7 @@ moments, the same hour, an hq change going through [playbook 08](08-small-fixes.
## Issues that stop
An issue stays in `fixing` only while an agent works on it. A step that stops, for a wait past its bound, a
An issue stays in `fixing` only while an agent works on it. A milestone that stops, for a wait past its bound, a
hand-over, or the session's end, moves each of its issues not delivered back to `open` with
`issue-tracker.move` and a note saying how far it got (its branch, its last commit, what is left). A list of
issues in `fixing` that nobody works on reads to the operator as stuck work.
@@ -286,13 +286,13 @@ issues in `fixing` that nobody works on reads to the operator as stuck work.
note saying what it waits for; one without such a note is a pause not written back.
- The milestone issues in `fixing` (`issue-tracker.list`) belong to one design at most: milestone issues
of two designs in `fixing` at once is the failure of "one design is built at a time".
- More than one open pull request in a repository that share no feature name, or a feature step whose issues
- More than one open pull request in a repository that share no feature name, or a milestone whose issues
stay in `fixing` for more than a working day, is the smell: stop and bring it to the operator.
- A review report that asks a change outside the issues' done-when, or a fourth round, is the failure of the
review rules; `issue-tracker.list` with `flag: abandoned` lists issues left in `fixing` with nobody on them.
- A pull request reviewed and green but not marked ready for more than 15 minutes is a lead that did not
mark it.
- A step that adds or changes a module marked ready with no integration test that starts the module whole is
- A milestone that adds or changes a module marked ready with no integration test that starts the module whole is
the failure of phase 3's fourth step.
- A bed run from `.work/<slug>/mesh-lab` that fails naming a `.work/<slug>/<repo>/…` path it cannot find is a
missing sibling worktree, not a mesh fault.
@@ -2,7 +2,7 @@
layer: to-be
status: in-progress
code: [mesh-controller, mesh-catalog modules/mesh-delivery]
updated: 2026-10-16
updated: 2026-10-17
decisions:
- "ADR 0408"
- "ADR 0407"
@@ -485,8 +485,8 @@ What the build proves before this design is implemented (research 055's directio
## Milestones
Confirmed by the operator on 2026-10-17 (playbook 04). Each is one feature step of playbook 07; the next starts
when the previous one's delivery is done. Milestones 5 and 6 are split into steps when they come up.
Confirmed by the operator on 2026-10-17 (playbook 04). Each is one release of playbook 07; the next starts
when the previous one's delivery is done.
| # | Outcome | Acceptance tests | Repositories | Issues |
|---|---|---|---|---|