portainer: publish its software ports; the machine side is the mesh's to assign #189

Merged
mesh-admin merged 1 commits from fix/portainer-software-ports into main 2026-09-30 18:54:41 +00:00
Contributor

9090:9000 and 9443:9443 were the predecessor's machine numbers written into the definition; on ace 9090 is taken by something else, and the operator's rule is that machine ports are the mesh's to assign. The manifest now says 9000 and 9443 (short form: the machine port is assigned, ADR of #165), listens.web is 9000. This is the portainer slice of #173, which is stale against main. Rolling out recreates portainer on novox with an assigned machine port; the route follows.

`9090:9000` and `9443:9443` were the predecessor's machine numbers written into the definition; on ace 9090 is taken by something else, and the operator's rule is that machine ports are the mesh's to assign. The manifest now says `9000` and `9443` (short form: the machine port is assigned, ADR of #165), `listens.web` is 9000. This is the portainer slice of #173, which is stale against main. Rolling out recreates portainer on novox with an assigned machine port; the route follows.
jschoubben added 1 commit 2026-09-30 18:54:31 +00:00
9090:9000 and 9443:9443 were the predecessor's machine numbers written into the
definition. The manifest now says 9000 and 9443 and the mesh assigns the
machine ports on each node (the portainer slice of #173, which is stale).
jschoubben force-pushed fix/portainer-software-ports from 667ac2ea25 to 80d9e9a7e7 2026-09-30 18:54:31 +00:00 Compare
mesh-admin merged commit ac7a9f2ca8 into main 2026-09-30 18:54:41 +00:00
mesh-admin deleted branch fix/portainer-software-ports 2026-09-30 18:54:41 +00:00
Sign in to join this conversation.
No Reviewers
No labels
2 Participants
Notifications
Due Date
No due date set.
Dependencies

No dependencies set.

Reference: novox/mesh-catalog#189