hq/03-DESIGN/01-to-be/00-work-breakdown.md
T
jschoubben e1febe8e0f Renumber the records 1 to 23
The consolidation left a sparse sequence -- 1, 4, 6, 7, 9, 10, 12, 15, 16, 18,
19, 25, 34, 35, 36, 37, 40, 42, 44, 45, 48, 49, 58 -- where the gaps were only
the archaeology of what used to be there.

Renumbered contiguously. Renames run in ascending order, so every target number
is already free and no two files ever collide.

The reference rewrite is one simultaneous pass rather than a sequence of
replacements. Numbers moved into slots other numbers were vacating -- the node
host went 37 to 16 while the lab went 16 to 9 -- so replacing one at a time
would have cascaded and silently pointed things at the wrong record.

Seven plain-text references survived the merges as prose rather than links,
naming records that no longer existed: the enrolment token, the link boundary,
what a declaration is, reachability, the repository structure. Each mapped to
the consolidated record that now holds it.

Verified rather than assumed: every [ADR NNNN](path) link now has matching text
and target, checked across the whole repository, and the checker passes.

Frontmatter `consolidates:` lists dropped -- they named records that are gone,
and each consolidated record already says in prose what it absorbed.
2026-08-28 23:28:34 +02:00

159 lines
6.7 KiB
Markdown

---
layer: to-be
status: designed
code: [hal]
updated: 2026-08-23
decisions: [02-DECISIONS/0008-mesh-brokers-nodes-host-agents-think.md]
---
# Work breakdown — the decomposition
How [ADR 0008](../../02-DECISIONS/0008-mesh-brokers-nodes-host-agents-think.md) gets built, in what order, and where a human must look.
Ordering is not preference. Each phase removes a constraint the next one needs gone.
---
## Rules of engagement
These exist so the work can run largely unattended without accumulating the kind of
damage this refactor is meant to remove.
### Autonomous by default
An agent may, without asking:
- read anything, measure anything, query any database read-only
- create branches, write code and tests, open pull requests
- run the test suite and typechecks
- write and update `hq/` documents
### Always stop and ask
- **destroying or overwriting data** — dropping a table, deleting a provision, rotating a
live credential, removing a module from a node
- **merging anything** — every merge is a human checkpoint, without exception
- **a decision the ADRs do not already answer** — record the question in the relevant
research effort rather than picking and moving on
- **any change to `hq/00-META`** — it is stable by nature
### Definition of done for every task
1. tests written **and failing first**, then passing
2. typecheck clean in every package the change touches
3. the local mesh (Phase 0) comes up, and the behaviour is demonstrated in it
4. `hq/` updated if the task changed or answered anything documented
5. deployed, and **delivery verified on every node** — not "the pipeline was green"
### Non-negotiables carried from the current system
- **Never edit mesh-managed files on disk.** Use the owning tool.
- **Never write to production databases directly.** Migrations for schema, application
code for data.
- **Every schema change ships twice** — consolidated schema *and* an incremental
migration.
- **Expand, then contract.** Add the new shape, migrate, verify, and only then remove the
old one — never in a single step.
- **A green pipeline proves transport, not effect.** Verify the effect.
---
## Phase 0 — A mesh that runs locally *(prerequisite)*
Nothing else starts until this exists. Every fault this refactor addresses was found in
production because there was nowhere else to find it.
| # | task | done when |
|---|---|---|
| 0.1 | Container image for a node runtime | a node process starts in a container and registers |
| 0.2 | Compose topology: broker, registry DB, object store, *n* nodes | `up` yields a mesh that elects a provider node and settles |
| 0.3 | Seed a minimal mesh: nodes, one module, one provision | a module deploys end-to-end with no external service |
| 0.4 | Run the pipeline inside it | a push-equivalent produces a cascade and a deployed artifact |
| 0.5 | Fixtures for the failure modes already known | credential rotation reaching a running session; a provider deploy rotating a shared credential; a migration that ships nothing — each reproducible on demand |
**Checkpoint:** a human confirms the local mesh reproduces at least one bug from
2026-08-22 before any decomposition begins.
---
## Phase 1 — Make the model expressible
The decomposition is impossible while a feature is a singleton per module.
| # | task | done when |
|---|---|---|
| 1.1 | Decision record — named features, per-node opt-in (next free number) | accepted |
| 1.2 | Manifest: declared `features:` with type + directory | a module declares two of one kind and both build |
| 1.3 | Selection: `always` / flavor-selected / `optional` | a node installs a subset; artifacts stay flavor-blind |
| 1.4 | `requires:` moves onto the feature | a schema feature's database is not provisioned where the feature is not installed |
| 1.5 | Assignment carries the opted-in feature set | opting a node in requires no rebuild |
**Checkpoint:** one existing module converted to declared features, deployed, verified —
before any others follow.
---
## Phase 2 — Draw the boundary the domain already has
Cheapest first, and each one proves the extraction pattern before the expensive ones.
| # | task | extracted from | risk |
|---|---|---|---|
| 2.1 | `hal/knowledge` — one store, review workflow ported | hippocampus + noxflow `knowledge_*` | low — additive |
| 2.2 | `hal/stream` — the record; notifications and messaging as views | axon, synapse, notifications, meetings, conversations | medium |
| 2.3 | `hal/agents` — identity, licence, runs, memory, thoughts | noxflow agents, `hal/thoughts` | **high** — touches credentials |
| 2.4 | `hal/work` — what remains of noxflow | noxflow tasks | medium |
| 2.5 | `hal/ai` — provider integration, flavored | `hal/claude*` | medium |
Each extraction is expand-then-contract: new context alongside, dual-write, verify, cut
over, remove. **Never a move commit.**
**Checkpoint:** after 2.1, a human confirms the extraction pattern before 2.2 begins.
After 2.3, a human confirms credentials still reach every agent on every node.
---
## Phase 3 — Reclaim the kernel
Only possible once domains have modules to own their code.
| # | task | done when |
|---|---|---|
| 3.1 | Move work-domain code out of `hal/sdk` | `workflow-engine.ts`, `task-commands.ts` live in `hal/work` |
| 3.2 | Move provider code out | `claude-credentials.ts` lives in `hal/ai` |
| 3.3 | Move delivery code out | feature handlers, artifact manager, build executor live in `hal/delivery` |
| 3.4 | Decide the residue | ADR: what `hal/sdk` keeps (open question 4) |
**Measure:** `hal/sdk` line count, tracked per task. Today: **34,636** across **155**
files.
---
## Phase 4 — Separate what the mesh runs from the mesh
| # | task | done when |
|---|---|---|
| 4.1 | Decide the destination (open question 3) | ADR accepted |
| 4.2 | Cross-repository dependency resolution proven | a catalogue module builds against a published `@hal/*` |
| 4.3 | Move the 91 catalogue modules | this repository contains only mesh contexts |
**Checkpoint:** move one application first and run it for a week before the rest follow.
---
## Sequencing constraints
- **0 before everything.** Unverifiable refactors are how this list got long.
- **1 before 2.** Extracting into contexts without per-node features recreates the module
count inside the new names.
- **2 before 3.** A domain can only own its shared code once the domain has a module.
- **2.3 after 2.1 and 2.2.** Agents touch credentials; do it once the pattern is proven on
cheaper contexts.
- **4 last.** It is the only phase that is pure movement, so it is the only one safe to
defer indefinitely.
## What "done" looks like
Eight contexts. `hal/sdk` holding only what is genuinely cross-cutting. A mesh that stands
up on a laptop. A module count that grows only when the domain does.